| Item |
Customer Information |
Work Scope |
Work Description |
Location |
Completion Date |
Contract Type |
| 1 |
|
Inspection
Services |
Remote Field
Electromagnetic Testing (RFET) for steam boilers
at Ethylene/Polyethylene (M) Sdn Bhd |
Kerteh |
June 1998 |
Lump Sum |
| 2 |
| PROJECT OWNER |
| PETRONAS Gas Berhad |
|
CLIENT: |
|
Heaven Engineering Sdn Bhd |
|
Maintenance Services |
Refurbishment
work for LPG heaters T-806/807/808 for Unit 1 and
Unit 2 LPG Export Terminal (Total expanded
manhours :4000) |
Kemaman |
May 1999 |
Lump Sum |
| 3 |
| PROJECT OWNER |
| PETRONAS Gas Berhad |
| Plant Operations Division |
|
Maintenance Services |
Replacement
of existing sealent for propane refrigerated tank
Q 803A using Fibaroll product at LPG Export
Terminal |
Kemaman |
January
2000 |
Lump Sum |
| 4 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| Transmission
Operations Division |
|
Maintenance Services |
Repair and replacement of damaged ductworks for gas turbine exhaust at Kuantan Compressor Station |
Kuantan |
February
2000 |
Lump Sum |
| 5 |
| PROJECT OWNER |
| PETRONAS
Gas Bhd |
| Transmission Operation Division |
|
Maintenance Services |
To repair, supply and service PSV 5140 B at Segamat Compressor Station |
Segamat |
Febuary
2000 |
Lump Sum |
| 6 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| Plant Operations Division |
|
Maintenance Services |
GRE coating works for flanges at Gas Processing Plant Trains 2 and 3 using Enviropeel products |
Kerteh |
July 2000 |
Lump Sum |
| 7 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| Transmission Operations Div |
|
Maintenance Services |
To dismantle, clean and inspect pipe spool for YTL Gas Metering Station in Paka, Terengganu |
Kerteh |
July 2000 |
Lump Sum |
| 8 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| Transmission Operations Div |
|
Maintenance Services |
To perform general maintenance and preservation of spare parts in SOC Warehouse, Segamat |
Segamat |
August 2000 |
Lump Sum |
| 9 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| Transmission Operations Div |
|
Maintenance Services |
Rectification works for NPB 8 Natural Gas Vehicle (NGV) lateral pipeline for PETRONAS Gas Bhd |
Kertih |
September 2000 |
Lump Sum |
| 10 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| Plant Operations Division |
|
Maintenance Services |
To install drain point valve at Gas Processing Plant #6 |
Kerteh |
September 2000 |
Lump Sum |
| 11 |
| PORJECT OWNER |
| PETRONAS Gas Berhad |
| Transmission Operations Div |
|
Maintenance Services |
Supply of manpower, equipment and consumables for repair works of refrigerant condenser at LPG Export terminal, Kemaman |
Kemaman |
December 2000 |
Lump Sum |
| 12 |
| PROJECT OWNER |
| Titan Petrochemicals Sdn Bhd |
| CLIENT : |
| Fiber Standard Sdn Bhd |
|
Maintenance Services |
Supply of manpower, equipment and consumables for the installation of Fibaroll coating materials |
Pasir Gudang |
January 2001 |
Lump Sum |
| 13 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| Plant Operations Division |
|
Maintenance Services |
Supply of manpower, equipment and consumables for the overhaul of LPG Loading Arm (cryogenic) at LPG Export terminal, Kemaman |
Kemaman |
Febuary 2001 |
Lump Sum |
| 14 |
| PROJECT OWNER: |
| PETRONAS Gas Bhd |
| CLIENT : |
| Plant Operations Division |
|
Maintenance Services |
| Supply of manpower, equipment and consumables for the overhaul of LPG Loading Arm (cryogenic) and pipe relocation at KSMF |
|
Kerteh |
June 2001 |
Lump
Sum |