• Construction and Minor EPCC Services
 
Construction and Minor EPCC Services
 
Item Customer Information Work Scope Work Description Location Completion Date Contract Type
12
PROJECT OWNER:
PETRONAS Gas Bhd
Transmission Operation Division
EPCC Services
EPCC for the Parit Buntar Gas Metering Station in Parit Buntar, Perak
Parit Buntar February 2004 Lump Sum
13
PORJECT OWNER
PETRONAS Gas Bhd
CUF Division
EPCC Services EPCC for the Installation of 3rd Demin Water Transfer Pump at CUF Gebeng, Kuantan Gebeng May2004 Lump Sum
14
PROJECT OWNER
PETRONAS Gas Bhd
Transmission Operation Division
EPCC Services EPCC for 12" Etane Piping Modification at Kerteh ROW ( Civil & Piping ) Kerteh July 2003

Lump Sum

15
PROJECT OWNER:
Petronas Penapisan (T) S/B
EPCC Services

EURO 2M Project

Kerteh

August 2004

Lump Sum
16
PROJECT OWNER
PETRONAS Penapisan (T) S/B
CLIENT
Shapadu Energy & Engineering Sdn Bhd
EPCC Services D941 Tank Conversion To BNC Tank Project at Petronas Penapisan ( Terengganu ) Sdn Bhd Contract : Subcontract of D941 Tank Conversion to BNC Tank Project. Kerteh January 2005 Lump Sum
17
PROJECT OWNER:
Gas Malaysia Sdn Bhd
EPCC Services PTo Supply, Install, Configure & Commission of Electronic Volume Corrector (EVC) for Gas Malaysia Sdn Bhd Kuala Lumpur September 2005 Lump Sum
18
PROJECT OWNER:
Petronas Gas Berhad
 
EPCC Services Engineering, Procurement, Construction and Commissioning of Ayer Puteh *(Junjung) City Gate Station Project Junjung January 2006 (completed) Lump Sum
 
Page [1][2][3]